The following paragraphs contain a quick summary of the steps in the Project Development process and the documents and forms needed to fulfill each step. For a more in depth breakdown of the process please review the following resources:
The typical SRF project consists of three steps, the facility plan, plans and specifications, and
construction. As the name implies, the facility plan is a
planning document that establishes existing conditions, identifies the current problems, projects
future conditions at the design year, and evaluates
alternatives to solve the existing problems and meet future needs. The evaluation of alternatives
includes both a cost effectiveness analysis and an
environmental assessment. The intent of the facility plan is to arrive at the most cost effective,
environmentally sound solution to the problem. The
facility plan must be approved by the North Dakota Department of Environmental Quality (NDDEQ)
before the project can proceed to the next step.
When the facility plan is approved, plans, specifications, and bidding documents are prepared based
on the recommended alternative from the facility plan. These must comply with, among other things, MBE/WBE and EEO requirements. Documents are approved by the
NDDEQ, the project can be advertised and bids opened. If the bids are acceptable, the construction
contract must be awarded to the low, responsive, responsible bidder following NDDEQ authorization. Construction can now
begin at the community's convenience.
At this time, the NDDEQ will schedule a preconstruction meeting with the community, consulting
engineer and contractor(s) to explain the construction
related requirements that must be complied with and to answer any questions that arise. In addition
to the preconstruction meeting, periodic
interim inspections will be conducted by NDDEQ engineers during the construction phase of the
project. Since SRF loans are cost
reimbursable, construction costs must be incurred before the community can receive payments. Once
costs are incurred, the community should submit
periodic payment requests to the NDDEQ for processing. Payment should be
received by the
community within two weeks of receipt of the request by the Department. When construction is
completed, the North Dakota Department of Environmental Quality will conduct a
final inspection to verify compliance with federal requirements, verify that the project was
constructed in accordance with the approved plans and
specifications, and establish final costs.
Repayment of principle must begin no more than one year after the project is declared operational.
Prior to this, the North Dakota Public Finance Authority will
work with the community to establish a repayment schedule.