Construction Permits In Progress

Permit applications will be reviewed in the order that they are received. Applicants will be contacted if any additional information is required to complete the permit application process.

The amount of review time required for a permit application is dependent on a variety of factors (completeness of the application, complexity of the review, number of applications currently under review, current staffing levels/expertise, etc.).

Questions may be addressed to the North Dakota Department of Environmental Quality at 701-328-5188, or email (AirQuality@nd.gov).


Type of Application Permit Issuance Time-frame*
Minor Source w/o public comment nor refined dispersion modeling ~90–120 days
Minor source with public comment ~120–150 days
Minor source with refined dispersion modeling ~150–180 days
Major PSD source ~9–12 months

* From the date of receipt of a COMPLETE permit application including application fee (NDAC 33.1-15-14-01.1.1 ).

Key

  • Received— Application has been received by the Department.
  • Under Review— Application has been assigned to staff, and the application is being reviewed and processed. Staff will contact applicant with any questions or if additional information is needed.
  • Public Comment— Application has been received, and reviewed by the Department and applicant and is now in the 30-day public comment period.
  • Public Comment— No 30-day public comment period is required unless requested by the public or if there is a significant degree of public interest in air quality issues.
  • Final Determination— Applicant has completed all requirements and the Department is close making its final determination on if a PTC should be issued or denied.

RSS/Email Notifications of Public Comment Periods

If you wish to be notified of public comment postings you may subscribe to the email list (note all Department of Environmental Quality notices are provided in this email list).

Open Records

Permit documents can be found in CERIS-ND. (Note only Air Quality related documents are in CERIS-ND and we are working to digitize paper records, so not all records are in CERIS-ND.)

Nesson Gathering System LLC

Roughrider Compressor Station

03.17.20
New (w/ modeling)
Received
Under Review (on Hold)
Public Comment
Final Determination

Nesson Gathering System LLC

Flickertail Compressor Station

03.17.20
New (w/ modeling)
Received
Under Review (On Hold)
Public Comment
Final Determination

Monarch Waste Technologies ND GP, LLC

Fargo Facility for Sanford Healthcare/HEIS

02.03.21
New
Received
Under Review
Public Comment
Final Determination

Minnkota Power Cooperative, Inc.

Milton R. Young Station

03.30.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination

NuStar Pipeline Operating Partnership L.P.

Jamestown North Terminal

04.09.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination (Issued)

Archer Daniels Midland Company (ADM)

Spiritwood Soybean Processing

05.14.21
New (PSD major w/ modeling)
Received
Under Review
Public Comment
Final Determination (Issued)

ONEOK Rockies Midstream, L.L.C.

Beavertail Compressor Station

06.18.21
New
Received
Under Review
Final Determination

Steffes LLC

Dickinson Facility

07.02.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination

Hiland Partners Holdings LLC

Rivers Edge Compressor Station

07.09.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination

Midwest AgEnergy

Blue Flint Ethanol, LLC

07.20.21
Modification to Existing
Received
Under Review
Final Determination

NDPC, LLC

Beaver Lodge Terminal

07.23.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination

Tesoro Great Plains Gathering & Marketing LLC

Fryburg Rail Terminal

07.23.21
Modification to Existing
Received
Under Review
Public Comment
Final Determination

Last Updated: 10/18/2021